It has been a year after the horrific Morbi bridge collapse in Gujarat, which left countless more injured and 135 dead, many of them were children. The trauma that remains profound over time .
A century-old bridge in Morbi, Gujarat, crumbled into the river below it on October 30, 2022, carrying hundreds of people with it. 55 children were among the 135 victims of the accident who passed away. It was determined that the primary causes of the collapse were congestion during Diwali and carelessness on the part of the bridge’s promoters. For all the families who lost relatives in the accident, a year filled with sadness and grief continues. Losing someone who is more treasured than ourselves might be the most catastrophic experience ever. Who is going to pay for this loss’s compensation? Would donations and money be able to heal the mental scars people have? When will the system that just keeps things on hold finally will give the people justice?
A five-member Special Investigation Team (SIT) was formed by the Gujarat government to investigate the collapse. The SIT turned in a preliminary report in December of last year, citing multiple failures in the structure’s upkeep, maintenance, and function by the Oreva Group (Ajanta Manufacturing Ltd.), whose managing director, Jaysukh Patel, is the primary alleged and is incarcerated at the moment.The cable-stayed bridge over the Machchhu River, known as Jhulto Pul, dates back to the British era and is considered a historic building for Morbi, a tiny town located 200 km from Ahmedabad.
In addition to Patel, three security guards and two ticket clerks were given bail by the high court a few months ago. Two managers of Patel’s company and two subcontractors who had fixed the bridge are now in jail.
In addition to the ten people who have been detained thus far, those who were found guilty of carelessness in the Special Investigation Team (SIT) report ought to be detained and punished as well.
According to the SIT’s final report, which was presented to the Gujarat High Court two weeks ago, the management of the Oreva company committed technical fault that resulted in the collapse of the bridge.
According to the SIT, the Oreva company’s management’s careless actions could not be tolerated.
The Gujarat High Court was informed in January of this year by Oreva Group that it was prepared to provide recompense to the victims of the bridge collapse. On February 22, 2023, the company was ordered by the court to provide a temporary financial help to the families of the 135 deceased individuals and Rs 2 lakh to each of the 56 injured individuals.
However, the relatives of the victims and the survivors who are still traumatised can only receiving justice through the compensation and trials.